Maintenance and Project Resurfacing, North Coast NSW

Project Description

Swietelsky Rail Australia (SRA) has been providing track resurfacing services for the Australian Rail Track Corporation (ARTC)'s Interstate NSW network since 2020.

The 2024 June long weekend provide ARTC with an opportunity to complete maintenance and construction tamping projects across the north coast network.

SRA was proud to support this program, single shifting our 08-275/3s UNIMAT Tamper and SSP303 regulator throughout the Kings Birthday long weekend between Raleigh and Grafton.

SRA delivered the project on time, incident-free, and without issue, ensuring a seamless handback.

Following the possession, our team was requested to remain on-site to complete additional scope for our valued client. Highlighting once again, our agility in responding to client requirements and our commitment to doing everything possible to enhance the reliability and performance of the rail network.


Project Stats:

  • Network | ARTC Interstate (North Coast NSW)
  • Track Resurfaced | Over 4,500m
  • Level Crossing Reconditioning | Resurfacing provided for two projects
  • Machine Reliability | Exceeded 98%
  • Completed sections handed back at line speed
  • Project Completion | June 2024